A Red Flag is a fact, event, or set of circumstances, or other information that may indicate a potential legal compliance concern for illegal or unethical business conduct, particularly with regard to corrupt practices and non-compliance with anti-corruption laws.
Disqualification of all competitive operators except the winner/ Disqualification of the lowest value bid
Procuring Authority / Buyer | Albanian Road Authority | ||||||||||||||||
Procuring Authority / Buyer | Autoriteti Rrugor Shqiptar | ||||||||||||||||
Tender object | “Studim Projektim aksi rrugor Elbasan - Lekaj Koridori 8” | ||||||||||||||||
Reference No. | REF-69727-05-18-2023 | ||||||||||||||||
Estimated / Ceiling Value ALL without VAT | 83 139 834,00 | ||||||||||||||||
Type of Contract | |||||||||||||||||
Procurement Method | Consultancy Procedure | ||||||||||||||||
Stage Procedure | Signed the Contract | ||||||||||||||||
Tender Publication Date | 19-05-2023 | ||||||||||||||||
Last date of Submitted Documents | 21-06-2023 | ||||||||||||||||
Tender Held Date | 21-06-2023 | ||||||||||||||||
No. of Bidders | 7 | ||||||||||||||||
Bidders |
1. BOE “GJEOKONSULT & CO” & “I T M” 2. BOE “InfraKonsult” & “ATELIER 4” 3. BOE “KLODIODA” & “P.C.S.COMPANY” & “TOWER” 4. BOE “NET-GROUP & “OMICRON KAPPA CONSULTING SOCIETE ANONYME” 5. BOE “PNI-2001” & “G & K” & “GeoENG” & “ABKONS” 6. “A & E ENGINEERING” SHPK 7. BOE “SWS Consulting Engineering-Structures, Water & Survey” + “SWS Consulting Engineering S.r.l” + “SINTAGMA SRL” + “Engineering Consulting Group” |
||||||||||||||||
Successful Bidder /Supplier / Provider |
|
||||||||||||||||
The winning bid ALL without vat | 75 680 000,00 | ||||||||||||||||
Bidder Announcement date | 14-09-2023 | ||||||||||||||||
Award and Contract Amount ALL with VAT | 90816000 | ||||||||||||||||
Contract date | 13-11-2023 | ||||||||||||||||
Planned Milestones of Contract / Start and End Date | 22 Muaj | ||||||||||||||||
Renewal Contract Additional Value (ALL with VAT) | |||||||||||||||||
Appeals |
Nuk ka pasur ankesa. Jane skualifikuar operatoret ekonomike te meposhtem: 1. A V E CONSULTING, per arsye: -Nuk ka paraqitur licencat -Nuk ka paraqitur sigurimin e ofertes 21. BOE “C.E.C GROUP” & “ARKONSTUDIO” -Nuk ka paraqitur licencat -Nuk ka paraqitur sigurimin e ofertes 3. BOE SWS Consulting Engineering Structures, Water Survey dhe SWS Consulting Engineering S.r.l dhe SINTAGMA SRL dhe Engineering Consulting Group, per arsye: -Nuk ploteson piken 2.3.2 Kapaciteti teknik, pikat e licences |
||||||||||||||||
Cancellation reason | |||||||||||||||||
Additions | |||||||||||||||||
Transaction / Actual Spending |
|
||||||||||||||||
Public Announcement Bulletin |
|