Construction and Maintenance of the "Thumanë–Fushë-Krujë–Vorë–Kashar" Road
Partner / Concesionary |
Ministria e Infrastruktures dhe Energjise |
Contract's Object |
The main object of the Concession/PPP is the Construction and Maintenance of the
Thumanë–Fushë-Krujë–Vorë–Kashar Road, according to the principle of “Turnkey
Project”. The essential conditions of the Concession include as follows:
The object of the Concession/PPP contract: Construction and Maintenance of the Thumanë–Fushë-Krujë–Vorë–Kashar Road.
The duration of the Concession Contract/PPP: 13 years (depending on the earlier termination of the Concession Contract in accordance with its terms).
Activities to be performed by the Concessionaire:Construction and
Maintenance of the Thumanë–Fushë-Krujë–Vorë–Kashar Road in accordance
with the standards approved by the Contracting Authority.
Sources of Concessionaire Revenues: An availability annual payment payable by the Contracting Authority for the Concessionaire, the level of which shall be determined in the bid submitted by the competitors. The first payment will be provided by the Contracting Authority when the Concessionaire has executed at least 25% of the works.
Applicable Legislation: The Concession Contract shall be governed by the legislation of the Republic of Albania.
The Project has as its objective the construction of a road, which starts in Thumane and continues to the intersection with the Tirana - Durres highway with a new crossing at a dislevel.
|
Procurement Method |
Open Procedure |
Concession's Status |
Announced the Winner |
Concessionary Company |
|
Last date of Submitted Documents |
11-06-2018 |
Concession's Held Date |
11-06-2018 |
No. of Bidders |
4 |
Bidders |
1.“Gjikuria” shpk 2.. “Alpin” s.r.l. 3. “Gruppo Adige Bitumi” s.p.a. 4.“Gener 2” sh.p.k. |
Successful Bidder /Supplier / Provider |
K58615301M“Gener 2” sh.p.k. |
Cost of Concession |
225,821,553.00 |
Concession's Duration |
13 |
Concession's Announcement Date |
18-04-2018 |
The winning bid ALL without vat |
225,822,000 |
Bidder Announcement date |
13-07-2018 |
Award and Contract Amount ALL with VAT |
|
Contract date |
|
Planned Milestones of Contract / Start and End Date |
|
Appeals |
Ankesa nuk ka |
Cancellation reason |
|
Public Announcement Bulletin |
|
Concessionaire Agreement/Acts |
|