District | Fier | |||||||||
Loan No | 8850-AL | |||||||||
Source of Loan/Financed by: | ||||||||||
Loan Amount by Currency | ||||||||||
Project Title | Regional and Local Roads Connectivity Project (RLRCP)>/b> | |||||||||
Description of the Project |
Regional and Local Roads Connectivity Project (RLRCP) marks an important step for the benefit of citizens. It foresees an impact on the potential growth of agricultural and tourism activities by improving access to selected areas, as well as strengthening the capacity of municipalities to manage their road assets.
|
|||||||||
Tender object |
Road safety improvements works.
The project aims the implementation of the Road Safety Audit recommendations of the pilot area of Fier – Seman road with highest safety standards. RSA was carried out on the 17 km long Fier – Seman road section in Fier county, whereas the scope of this pilot project covers only 1.6 km of it, in Dermenas village (from km 4+400 to km 6+100). Another option to be decided, might be the section from km 5.110 to km 5+580. In the initial project, the road was a two-way paved carriageway, with 3.50 m wide lanes and 0.50 m wide gutters on both sides. A 2.50 m wide paved cycle lane was also provided along one side of the road. On both sides of the carriageway were located 1.50 m wide paved footpaths. The Site is located at Fier municipality. |
|||||||||
Reference No. | RLRCP/1/1.8/2018 | |||||||||
CPV Code |
|
|||||||||
Estimated / Ceiling Value ALL without VAT | ||||||||||
Type of Contract | ||||||||||
Procurement Method | ||||||||||
Stage Procedure | Announced Procurement | |||||||||
Tender Announcement Date | 19-05-2022 | |||||||||
Opening Date for Submission of Bids | 19-05-2022 | |||||||||
Closing Date for Submission of Bids | 04-07-2022 | |||||||||
Sector | ||||||||||
No. of Bidders | ||||||||||
Bidders | ||||||||||
Successful Bidder /Supplier / Provider |
|
|||||||||
The winning bid ALL without vat | ||||||||||
Bidder Announcement date | ||||||||||
Contract date | ||||||||||
Contract Value including VAT | ||||||||||
Contract Milestones Due Dates | The construction period is 3 months | |||||||||
Appeals | ||||||||||
Cancellation reason | ||||||||||
Notes | Bidding will be conducted through international competitive procurement using Request for Bids (RFB), Small Works (One-Envelope Bidding Process) as specified in the World Bank’s “Procurement Regulations for IPF Borrowers” July 2016 (“Procurement Regulations”), and is open to all eligible Bidders as defined in the Procurement Regulations. | |||||||||
Transaction / Actual Spending | ||||||||||
Relevant published Bulletin |
|