Design, Build, Finance, Operate, Maintenance, Rehabilitation and Transfer of road segment Milot – Thumane – Kashar – Luzi Vogel – Fier, Type of contract is "Work" ( Concession/PPP).

Partner / Concesionary Ministria e Infrastruktures dhe Energjise
Contract's Object Design, build, operation, maintenance, rehabilitation, and transfer of the road segment Milot-Thumane-Kashar- Luzi i Vogël- Fier .
Location of the contract object:The layout of this road starts from the interchange SH6 with SH1 and ends at Fier Bypass:

Numri i referencës : REF-64779-07-08-2020.

Contract type:Design, construction, operation, maintenance, rehabilitation and transfer. ( Concession/PPP).
The estimated project value:1.188 billion Euros (VAT excluded) 4. Funding source: Private investment
Contract duration or execution timeline:Duration 35 years



_________________________________________________

The Ministry of Infrastructure and Energy has decided to implement the project on concession/public-private partnership for the design, build, operation, maintenance, rehabilitation and transfer of road segment Milot-Thumanë-Kashar-Luzi i Vogël-Fier.
The Bid Winner selection shall be based on a competition procedure (open procedure) according to qualification and evaluation criteria specified in this document.
The concession/PPP contract duration will be 35 (thirty-five) years upon its entry into force.
This contract shall enter into force upon its signing by parties and after the publication of the Decision of the Council of Ministers on its approval in the Official Gazette of the Republic of Albania. The Adriatic-Ionian Corridor has been identified as part of TEN-T Mediterranean Corridor, which lies in the main corridor of EU network in the Western Balkans Region.
The estimated length of the entire |Mediterranean Corridor is approximately 1,550 km. In the Western Balkans, the corridor traverses Montenegro (approximately 7% of its total length) and Albania (approximately 20% of its total length or nearly 300 km).
The establishment of network aiming to strengthen road safety, transport planning, regional connection, movement, competition and integration to TEN-T network of EU.
The proposed project - a toll road segment from Milot to Fier approximately 115 km long - comprises 37% of the Albanian AIC, and 7.5% of the overall corridor of the Mediterranean Corridor.
A part of the proposed road consists of new alignments and upgraded existing roads in the Category A highway and main interurban roads, Category B.
The road also includes necessary tunnels and bridges, underpasses/overpasses, intersections, safety fences, service roads, controlled exits and entries, toll stations, parking areas, and the Intelligent Transport Monitoring System (ITS).

The road consists of the following six (6) sections:

• Section 1-Milot – Thumane, -13.5 km length
• Section 2- Thumane – Kashar-20 km length
• Section 3-Kashar – Peze Helmes-9 km length
• Section 4-Peze Helmes – Luzi Vogel-24 km length
• Section 5- Luzi Vogel / Lekaj – I/C Rrogozhine -8 km length
• Section 6- Rrogozhine – beginning of Fier Bypass- 38 km length
Procurement Method Open Procedure
Concession's Status Cancelled Procurement
Concessionary Company
  • Last date of Submitted Documents 09-11-2020
    Concession's Held Date 09-11-2020
    No. of Bidders
    Bidders
    Successful Bidder /Supplier / Provider
  • Cost of Concession 1.188 miliardë Euro
    Concession's Duration 35 vjet
    Concession's Announcement Date 09-07-2020
    The winning bid ALL without vat
    Bidder Announcement date
    Award and Contract Amount ALL with VAT
    Contract date
    Planned Milestones of Contract / Start and End Date
    Appeals
    Cancellation reason Asnjë nga ofertat e paraqitura nuk përputhet me kriteret e përcaktuara në dokumentet e tenderit.
    Public Announcement Bulletin
    Concessionaire Agreement/Acts

    Contract Notice
    Preceding Documents for Competition Concession/ Private Public Partnership Procedure for the Design, Contruction, Financing, Operation, Maintenance, Rehabilitation and Transfer of Road Segment: Milot – Thumane – Kashar- Luzi Vogel -Fier
    The steps to open “Asig Ortholmagery 20 cm”
    Appendix - Technical Conditions of Contract (T.C.C.)
    Feasibility Study for the Adriatic-Ionian Road Corridor (Route 1 and Route 2) Montenegro and Albania
    Feasibility Study for the Adriatic-Ionian Road Corridor (Route 1 and Route 2) Montenegro and Albania - ( pg .401 - 956 )
    Maps
    Kriteret Teknike
    Niveli fillestar i Garancisë (sipas te ardhurave).

    Privacy Policy

    Except when otherwise defined, all data & information offered in Open Procurement Albania is available under the licenses: This material is Open Data