District | Vlore-Gjirokaster | |||||||||
Loan No | IBRD loan 8850-AL | |||||||||
Source of Loan/Financed by: | World Bank | |||||||||
Loan Amount by Currency | ||||||||||
Project Title | Regional and Local Roads Connectivity Project (RLRCP)>/b> | |||||||||
Description of the Project |
Regional and Local Roads Connectivity Project (RLRCP) marks an important step for the benefit of citizens. It foresees an impact on the potential growth of agricultural and tourism activities by improving access to selected areas, as well as strengthening the capacity of municipalities to manage their road assets.
|
|||||||||
Tender object |
Reconstruction of the road Gusmar – Kuc . Rikonstruksion i rrugës "Gusmar – Kuc". |
|||||||||
Reference No. | RLRCP/1/1.4/2019 | |||||||||
CPV Code |
|
|||||||||
Estimated / Ceiling Value ALL without VAT | ||||||||||
Type of Contract | ||||||||||
Procurement Method | ||||||||||
Stage Procedure | Announced the Winner | |||||||||
Tender Announcement Date | 05-08-2019 | |||||||||
Opening Date for Submission of Bids | 05-08-2019 | |||||||||
Closing Date for Submission of Bids | 20-09-2019 | |||||||||
Sector | ||||||||||
No. of Bidders | 10 | |||||||||
Bidders |
Salillari Rawafed Al-Torok Contracting Est Avtomagistrali-Tcherno More JCS-Shumen Alb-Star Gjoka Konstruksion INC spa Gener 2 Vellezerit Hysa shpk & Ricciardello Construzioni srl Tekar Teknik Arastirma Ticaret Limited Sirketi GI.MA.CO. Costruzioni srl |
|||||||||
Successful Bidder /Supplier / Provider |
|
|||||||||
The winning bid ALL without vat | 4,817,034 USD | |||||||||
Bidder Announcement date | 06-12-2019 | |||||||||
Contract date | ||||||||||
Contract Value including VAT | ||||||||||
Contract Milestones Due Dates | 12 muaj | |||||||||
Appeals |
The Bidders whose Bids were rejected and the reasons therefor: 1) JV “Vellezerit Hysa” shpk & “Ricciardello Construzioni” srl: ITB 18, ITB 19 Bid Security – The criterion is not fulfilled. The bidder has not submitted a Bid Security. 2) “Tekar Teknik Arastirma Ticaret Limited Sirketi”: ITB 11 …The documents shall be submitted in the acceptable form for the Albanian institutions. (notarized/legalized/apostille, etc.) – The criterion is not fulfilled. Except company registration document, the documents are not submitted in the acceptable form as stated in procurement documents – notarized/legalized/apostille, etc. 3) “GI.MA.CO. Costruzioni” srl. ITB 11 …The documents shall be submitted in the acceptable form for the Albanian institutions (notarized/legalized/apostille, etc.) – The criterion is not fulfilled. The documents are not submitted in the acceptable form as stated in procurement documents – notarized/legalized/apostille, etc. |
|||||||||
Cancellation reason | ||||||||||
Notes |
The Project consists of the construction of the road segment Kuc –
Gusmar. The alignment of the Gusmar-Kuç road lies in the southwestern part of Albania,
in the Kurvelesh area of Vlora district. It links one after another the villages from
Progonat, Gusmar, Kuc. The road segment begins at the exit of the village of Kuc (in the area called Buronjat) and continues along the Kuci River, Habilaj River and Kasemi River. The road segment between Kuci and Gusmar is a summer (seasonal) roadway, accessible only by high vehicles, and passing through most of the Kuci River bed. The road continues along the streams then start increasing levels to get to the village of Gusmare. The Site is located at Vlora and Tepelena municipalities. Bidding will be conducted through international competitive procurement using Request for Bids (RFB), Small Works (Two-Envelope Bidding Process) as specified in the World Bank’s Procurement Regulations for IPF Borrowers July 2016 ( Procurement Regulations ), and is open to all eligible Bidders as defined in the Procurement Regulations. |
|||||||||
Transaction / Actual Spending | ||||||||||
Relevant published Bulletin |
|